Project no.: YABIMO/Z/1230

Production of steel elements for “Reskapshus Jarle Ring” project

We had won the next project from our regular business partner, this time it was production of steel elements for “Reskapshus Jarle Ring” project. The project consisted in making a lot of small elements which, among other things, consisted of anchors, gusset plates, angles, columns and plates for columns. The total weight of steel was 9 000 kg. We used steel S355J2+N and as for corrosion protection hot dip galvanizing min. 100 microns acc. to EN 1461. Fabrication time took 6 weeks, delivery was on time.