Refurbishing of precast concrete factory in Borgarnes including design, delivery and installation.
Job carried out between October 2018 and January 2019.
Yabimo during this period have done a lot of major alterations to main steel and concrete structure.
Concrete walls, old silos and conveyors within the scope of work were demolished and 41 tons of new steel structure installed.
Also a new concrete transport track was designed and assembled on site.
As minor works Yabimo have installed wall and roof sandwich panels as final envelope to the factory.
Would you like to learn more about this and other projects?
YABIMO maintains ongoing cooperation with leaders in the energy sector, including renowned service providers such as Aker Solutions. We deliver…
The Johan Castberg project is one of the largest energy ventures being developed on the Norwegian continental shelf, led by…
Discover how YABIMO can support your projects with our expertise and resources. We’re here to answer any questions you may have about our services and capabilities.
Prefer to connect with a representative in your region? Visit our Contact page for direct contact details.