« back
Project no.: YABIMO/Z/1475

Production of steel containers

Yabimo produced 4 pcs of steel containers. The weight of one container was 1214 kg. Production was according to EXC2, EN 1090. Without surface treatment and corrosion protection. NDT of welds - 100% VT + 10% UT + 5% MT. Production took 5 weeks, delivery on time according to the required schedule.